The process by which the contractor transfers possession and control of the completed works to the employer. In FIDIC contracts, handover is formalised through the Taking-Over Certificate. A successful handover typically requires the works to be substantially complete, with as-built drawings, operation and maintenance manuals, and any other contractual deliverables provided. The date of handover affects the running of the Defects Notification Period.
A legal concept — recognised in some civil law systems and in the UNIDROIT Principles — where changed circumstances have fundamentally altered the equilibrium of the contract, making performance excessively onerous for one party. Unlike force majeure, hardship does not make performance impossible; it merely makes it much more difficult or expensive. Common law systems generally do not recognise hardship as a ground for relief absent an express contractual provision.